  • Maintain relationship with subrecipient PI and staff throughout the life of the subaward
  • Monitor subaward progress related to meeting project goals
  • Monitor subaward activity and expenses in relation to and alignment with the project Scope of Work (SOW) and budget
  • Follow subrecipient monitoring plan (if applicable)
  • Alert Subaward Team about any concerns of a programmatic or financial nature
  • Conduct subrecipient initial and annual assessment per federal requirements
  • Draft, negotiate and issue subaward agreement and modifications
  • Assist with close-out process

Invoicing

PI Approval (Technical Progress)

DLCI Financial Officer/Administrator (Compliance)

  • Per MIT policy, PI must review and approve all subaward invoices.  
  • PI checks that costs on invoice are as expected in accordance with the approved subaward budget and project progress
  • PI review and approval constitutes confirmation that appropriate technical progress is being made and that deliverables required under the invoice have been completed and provided. 
  • PI Attestation - Sample language: "To the best of my knowledge, I certify that the subawardee's invoice costs appear reasonable and fairly correlate with the technical progress made on this research project."
  • Record of PI approval must be saved for possible future audit

Ensures that:

  • Invoices are reviewed and processed in a timely manner
  • PI reviews and documents their approval based on technical performance
  • Invoice meets compliance criteria
  • PI approval records are available to auditors, when requested
  • Any required cost share is documented on invoices and tracked

Timely processing:

  • Compliant invoices should be paid within 30 days of the invoice date
  • Note issues that delay invoice payment

Compliant invoices must include (download sample and checklist [DOCX]):

  • Allowable costs that align with approved subaward budget
  • Proper Subaward ID#, Purchase Order #, unique Invoice Identification #
  • Invoice submission date and date range covered by invoice
  • Signature, printed name, and title of authorized signatory (cannot be signed by Sub PI)
  • Required attestation language (2 CFR 200.415 for federal – similar allowed for non-federal)
  • Final Invoice must be marked “Final”

Approval and Questions:

  • Reject invoices that do not meet compliance criteria. Explain rejection to subrecipient for correction and resubmission
  • Work with B2P (B2P@mit.edu) on issues such as:
    • Expired cost object
    • Indirect costs not charging correctly
    • Cannot modify PO – requisitioner name needs to be updated
  • Alert Subaward Team (subawards@mit.edu) about issues with technical progress, subrecipient performance, or late invoices that may prevent payment
  • Approve in B2P (COUPA) after PI approves and if invoice meets compliance criteria 

Modifications

PI/DLCI

Subaward Team

  • Submit B2P Change Order request (Quick Card) to issue a Subaward Amendment to:
    • Extend the Period of Performance (POP) end date
    • Increase/decrease funding
    • Revise SOW/budget
    • Other changes (e.g., new PI)
  • Provide detailed modification instructions
    • Upload Subaward Modification Checklist that includes all information needed to issue accurate Amendment
    • Attach any updated documentation (e.g., revised budget, compliance approvals, etc.) to Purchase Order (PO)
    • Incomplete/unclear instructions may delay Amendment issuance
  • Contact B2P@mit.edu for questions regarding PO errors or issues
  • Draft and issue Subaward Amendments
  • Obtain clarifications from DLCI if needed
  • Ensure entity assessment is up to date
  • Copy PI and DLCI admin when sending fully-executed modification to subrecipient

Close-out

MIT will not close out a prime award until all subawards issued under the prime award have been closed out. Subawards will only be considered formally closed when all applicable closeout requirements have been accomplished.

PI/DLCI

Subaward Team

  • Proactively engage Subrecipient toward POP end date
    • To collect final deliverables and reports as applicable
    • Remind Subrecipient to submit final invoice (marked as "FINAL")
    • Confirm final invoice has been submitted for payment
  • Submit Closeout Request form to Subaward Team
    • Confirm reporting requirements have been met
    • Confirm balance to be De-obligated
  • Confirm receipt of complete and accurate Closeout Request Form
  • Collect/confirm receipt of final patent, property, or other report from Subrecipient (as required)
  • Soft close B2P PO
  • Change KC subaward record statuses – Ended, Financially Closed, Closed